FIRST ADMITTANCE FACILITY, WOOD PANELED STRUCTURE, LAUTZENHAUSEN
Another example of a prefabricated wood construction for refugees: this 3-story building for 200 inhabitants was completed after a 3-week planning phase and 4 months of construction.
Status | Type of residents |
Number of residents | Construction costs (Euro/m²) |
Building method | Country |
Architect | Commissioned by |
Construction firm |
This first admittance facility was built in a very short time using high-quality construction materials in a high-density structure. This 3-story building was planned in 3 weeks, constructed in 4 months. The building (33 m long, 15 m wide, 9 m high) was built using prefabricated wooden panel elements (3 x 6 m grid modules). Domestic wood was used for the interiors and exteriors. Ideally, the building will be used subsequently as a hostel or office.
(Excerpt from project description)